Francis turbine
H = 15.5 m
Q = 1.65 m3/s
P = 230 kW
For our customer, the Soške elektrarne Nova Gorica utility company, we carried out the revitalisation of the Mesto-Idrija SHPP. In the scope of this project, the guide vane section was reconstructed to accommodate self-lubricating bearings. We also replaced the worn out runner with a new one. We replaced the hydraulic part of the control system. At the site, we carried out corrective turning of the flywheel to reduce wobbling. We also restored the turbine thrust bearing.